The City of Minneapolis has
completed plans for Phase II of the Midtown Greenway.
Under the projects current schedule, the Greenway
should extend to new communities and neighborhoods in
Midtown Minneapolis by the end of the year. Trails, ramps,
lighting, and retaining walls are designed and ready
for construction, and Phase II will stretch from Fifth
Avenue on the west to Hiawatha Avenue on the east. This
addition required more concentrated planning and design
work than Phase I, but after careful consideration and
compromise, the Greenway has a design that will serve
diverse needs.
Developing Designs
The primary challenge to completing
Phase II was the Cepro Grain Elevator site, which was
the last remaining customer of the Canadian Pacific Railroad
in the Corridor. Hennepin County provided critical leadership
and financial resources to the project by acquiring the
elevator site and freeing the railroad to pull up its
tracks and abandon the Corridor. Canadian Pacific will
tear up the tracks this Spring and mitigate any environmental
problems associated with its use of the Corridor, allowing
Phase II construction to begin on-time.
The rail abandonment procedure
and federal funding used for construction triggered historic
review by the State Historic Preservation Office (SHPO).
The Corridors associations with early 20th century
engineering, urban planning, and transportation, plus
its unique solution to public safety concerns make it
eligible for placement on the National Register of Historic
Places. SHPO worked to ensure that the Phase II design
would not harm the Corridors historic integrity.
One result of that work is that retaining walls for ramps
and the grade separation will be constructed from a modular
block different than the one used in Phase I. This new
concrete block will be much larger than the Phase I block,
and is designed to better fit the historical, industrial
nature of the Corridor.
Planning for future transit
is also a critical component of the Phase II design.
Hennepin County is delaying its Midtown transit planning
until it has completed a transit study for the Southwest
Corridor, but ensuring that transit has room in Phase
II was a critical design challenge. The Midtown Greenway
Coalition and Hennepin County worked together to find
solutions to future transit plans that would not interfere
with the biking and pedestrian experience. Retaining
walls will not be as high as originally planned, transit
will have the necessary space, and construction costs
will not expand significantly.
Through the efforts of Mary
Altman at the Citys Office of Cultural Affairs,
the ramp railings will contain a public art component
consistent with the ideas set forth in the Public Art
Master Plan.
The Schedule
The Phase II design process
is complete, but the public bidding, final engineering,
and public approval process will take several more months.
A wide variety of interested public entities must weigh
in on the Phase II expansion. The Minnesota Department
of Transportation must approve the budget and plans,
because federal funding is part of the finance package,
and MnDOT will act as the federal agent for this project.
Hennepin County owns the rail right-of-way, and thus
ultimately the Greenway, so it must approve plans.
By the end of July, the City
will let the contract for bids, and within three weeks
of that time, select a contractor. Construction will
begin by the end of the Summer, and could be complete
as early as this Fall. |